Road Work Ahead: Executive Summary
Road Work Ahead: Is Construction Worth the Wait?
Back
to Table of Contents
Executive Summary
Road Work Ahead
Is Construction Worth the Wait?
The United States is experiencing a boom in road
construction as an infusion of new federal dollars reaches the states. In many cases these
road projects are designed to ease traffic congestion by widening or otherwise expanding
the capacity of existing roads.
But ironically, the construction projects themselves can create
significant congestion and delay. Transportation officials rarely consider the impact of
these delays when they promote the congestion-relieving benefits of a new road. To see if
these delays ultimately result in better commutes for those who regularly use the roads,
STPP conducted case studies of road expansion projects now underway around the nation.
We used figures provided by state Departments of Transportation
(DOTs) and selected case studies according to the nature of the project, geographical
distribution, and availability of data. We studied both large and small projects that
expand road capacity by adding travel lanes and modifying interchanges.
Results from these case studies indicate that road expansion
projects often deliver scant time savings to people who use the road everyday, while
allowing and even stimulating significantly more traffic once the construction project is
completed. In many cases driver delays due to construction are so long, and the time
savings predicted from the finished project so minor, that it can take years for commuters
to break even and begin to make up the time they lost during construction.
For the massive I-15 highway in Salt Lake City, Utah, we found
that commuters now using the road won’t break even on the time they wasted during
construction until 2010, a full eight years after the project is completed. In Nashville,
Tennessee, adding lanes to I-24 is causing delays that current highway users won’t
recoup until they have driven the new section for more than two years. That puts the
break-even point in 2003. In Trenton, New Jersey, the expansion of Route 29 necessitates a
detour that costs the average commuter more than 80 hours a year. The new road will save
just about 25 hours a year. The break-even point for motorists using this route will not
come until 2012, an incredible ten years after completion. Most alarming is the
Springfield Interchange located in Northern Virginia outside of Washington, DC. Unless the
Virginia Department of Transportation can remove 2,500 cars from the road every day during
construction, the average commuter could waste an astonishing 1,750 hours in traffic
during the eight years of construction. Motorists who stick it out hoping to realize some
time savings once the project is completed will never recoup the hours lost to the
reconstruction project.
The results of this study demonstrate how traditional
transportation planning fails to focus on what is most important to citizens: their own
commute. Engineers focus on increasing road capacity, which they measure through
engineering metrics such as "average daily traffic," (ADT), and "Level of
Service," (LOS). Unfortunately, these calculations do not adequately reflect the
experience of individual drivers. As a result, road projects that succeed in increasing
capacity can fail when it comes to significantly improving individual commutes.
Road construction addresses just one part of the congestion
problem. Population growth is often cited as the underlying reason for increasing road
capacity. However, in the past 15 years, road building has more than kept up with
population growth in metropolitan areas: in fact, the number of miles of roadway per
person in those areas has increased by nine percent. But the amount the average person
drives has grown much faster than the population, with daily miles traveled increasing two
to five percent per year since the 1950s. This increase in driving is in large part a
result of sprawling, unplanned development that requires many car trips to meet basic
needs.
| Project |
Construction Delays (per trip) |
Years of Construction |
Post-Construction Average Time Savings (per trip) |
Break-Even Year |
Expected Growth in Traffic |
| Springfield
Interchange, Northern VA |
30 min |
8 years |
30 sec |
Never |
55% |
| I-15,
Salt Lake City, UT |
15 min |
4 years |
7 min |
2010 (8 years) |
53% |
| SR-29,
Trenton, NJ |
10 min |
3 years |
3 min |
2012 (10 years) |
56% |
| I-24,
Nashville, TN |
15 min |
14 months |
7 min |
2003 (2.75 years) |
33% |
Road construction may in fact have even fewer benefits than those
projected here, because additional highway space can lead to additional traffic. While
this study relied on official projections of future traffic from state DOTs, in many cases
these predictions do not take into account the increase in driving that the new roads will
lead to. This phenomenon, called "induced travel," occurs when road capacity is
expanded and drivers flock to the new facility hoping to save time. Also, the new roadways
tend to draw people who would otherwise avoid congested conditions or take alternative
modes to their destinations. In the long run, this encourages additional development
nearby, and that leads to even more traffic. Using a conservative Federal Highway
Administration estimate of the impact of induced travel, an STPP analysis found that by
the year 2011, a mere decade after construction is completed, average rush-hour speed on
I-15 in Salt Lake County could drop to 45 mph. This is lower than the average in 1996,
before construction began.
These case studies indicate that while construction projects are
often billed as relieving congestion for residents and workers, what they may ultimately
do is encourage more traffic. Current highway users get little benefit.
Recommendations:
We recommend that:
- Transportation officials tell citizens how their commute will be
affected by road building plans. Investments in road expansion projects should not be made
until transportation officials consider the effect of construction delays and induced
travel.
- State and local transportation officials place a high priority on
reducing delays caused by road construction, by streamlining construction processes and
making transit service convenient.
- Transportation officials find ways to provide congestion relief
without inflicting the increased congestion that results from construction projects. Among
the many techniques available are providing better transportation alternatives, allowing
flexible work hours, and clearing accidents quickly.
The Surface Transportation Policy Project is a nationwide network of more than 800
organizations, including planners, community development organizations, and advocacy groups,
devoted to improving the nation’s transportation system.
|