10/1/1994
Major Investment Studies: An ISTEA Legacy with Promise
by Julie Hoover
ISTEA Planners Workbook
Major investment projects merit priority attention
from transportation professionals and citizen groups because they
involve the expenditure of large sums of money, typically tens
of millions of dollars, and can significantly affect mobility
and quality-of-life in metropolitan areas.
ISTEA and the Clean Air Act Amendments triggered
the need for new major transportation investment planning procedures,
which were defined in a preliminary way in the FHWA/FTA Final
Rule on Statewide and Metropolitan Planning (Final Rule) issued
in the Federal Register on October 28, 1993. Further guidance
has been offered in FHWA/FTA seminars held across the country
and in a subsequent summary of key questions and answers.
This new corridor planning process, which was conceived
to improve transportation investment decisions, came to be called
a "Major Investment Study," or MIS. (It was originally
characterized as a "Major Investment Analysis" but the
corresponding acronym-MIA-was perceived to have a pejorative connotation
so the name was changed.)
Major investment studies are required when an agency
identifies the potential need for both a major investment and
federal funds. Their primary purposes are to provide information
about the likely impacts and consequences of alternative transportation
investment strategies, and to assist the MPO in adopting the strategy
to be implemented as part of its long range plan. A strategy refers
to the design concept and scope of a project, and may also include
operational and policy (land use, parking availability and pricing,
transportation demand management, etc.) components as well as
a financial component.
A major investment is officially described as a "high
type highway or transit improvement of substantial cost that is
expected to have a significant effect on capacity, traffic flow,
level of service, or mode share at the transportation corridor
or sub-scale area." Examples include but are not limited
to: a new, partially controlled principal arterial; extension
of a partially controlled principal arterial (one or more miles);
capacity expansion equivalent to one or more lanes on a partially
controlled principal arterial; construction or extension of an
HOV facility or fixed guideway transit facility; addition of lanes
or tracks to a fixed guideway; and substantial increase of transit
service on a guideway.
HOW CITIZENS SHOULD BE INVOLVED
Citizens concerned about transportation risk burn
out as they are faced with an increasing array of involvement
opportunities at state, MPO, and project levels. Not all are equal,
of course, for there is broad variation in the intent and responsiveness
of the various planning sponsors, the intensity of participation
solicited, and the relevant importance of the issues addressed.
All things being equal, citizens should take special notice of
MISs because the stakes in this arena are so high. To be most
effective, make your views known at both federal and local levels.
FHWA Meets FTA to Craft a Common Planning Process:
for the past two decades, planning for highway and transit major
capital investments has evolved differently.
In general, planning requirements for transit investments
have been much more rigorous. Project sponsors had to prepare
an Alternatives Analysis/Draft Environmental Impact Statement
(AA/DEIS) before preliminary engineering, which involved close
scrutiny of alternative modes and alignments, a 15-year planning
horizon, a financial planning assessment, and cost-effectiveness
analyses. Additionally, project sponsors had to obtain federal
approval before even embarking on an AA/DEIS. Finally, there was
a "one corridor at a time" restriction and a policy
of "overmatch," whereby localities which pledged more
than minimum local funding were given federal priority.
In contrast, highway investments proceeded in a relatively
laissez-faire environment, enjoying an absence of federal approvals
to initiate planning studies and limited federal overview of planning
products, no corridor restrictions, and a 20-year planning horizon.
Financial considerations and cost-effectiveness requirements were
non-existent and formal EISs were postponed until preliminary
engineering.
In ISTEA, Congress instructed FHWA and FTA to conform
their environmental procedures. This provided some of the impetus
for developing an integrated planning process. Other ISTEA and
Clean Air provisions came into play as the full implications of
the reauthorization bill were realized including flexible funding,
CAAA requirements for detailed plans, and ISTEA's emphasis on
intermodalism.
Who Can Officially Sponsor an MIS:
only government agencies. These include state DOTs, MPOs, transit
properties, commuter rail and railroad agencies, transportation
authorities, and city and county governments.
MISs Feature Interagency Agreements, Public Involvement,
and Comprehensiveness: an MIS is a thorough
assessment of alternatives in a corridor or subarea. In some respects,
it is similar to FTA's former Alternatives Analysis process, although
sponsors have the option of deferring the Draft Environmental
Impact Statement to the next phase of project development (see
following section), a 20-year time horizon prevails, the level
of federal oversight is reduced, and there are other minor differences.
The MIS must conform to federal regulations and guidance. Key
elements include:
- An initial interagency meeting (or meetings)
to determine the extent of the MIS. Participants must include:
the state DOT; the MPO; relevant transit agencies; environmental
resource and permit agencies; affected local officials; the FHWA;
FTA; operators of other major modes of transportation; and, where
appropriate, community development agencies, major governmental
housing bodies, and other related agencies that may be affected
by the proposed scope of the analysis. Participation of citizen
groups is not mandatory in this formal negotiating process, but
is not prohibited either. Some type of public involvement must
be conducted during the period.
- It is critical for the sponsoring agency to have
a clear statement of purpose and need at these meetings so participants
can adequately assess whether the alternatives adequately respond
to the corridor's transportation problems. Indeed, the statement
itself should be subject to review, especially from the perspective
of its comprehensiveness. Another key issue is the level of detail
to be addressed in the MIS.
- Any agreements reached should be set down in
writing. Denver, which has already gone through the process, has
fallen back on their written agreements several times.
- A proactive public involvement program initiated
early in the process.
- Consideration of all reasonable alternatives.
While sponsors do not have to waste time studying unrealistic
options, all rational solutions to the corridor's transportation
problems must be addressed. This represents a fairly significant
change for highway project sponsors.
- Demand forecasting that includes the level of
usage, the basis for the estimation of benefits and costs, freight
movement as well as person trips, impact on other facilities,
and input to other impact assessments.
Assessments of alternatives to the extent needed
to answer community concerns and arrive at a defensible Locally
Preferred Alternative. Impact assessments should cover:
- mobility, including needs of the transit-dependent
population;
- social, economic, air quality, other environmental,
energy concerns;
- operating efficiency and safety;
- land use and economic development;
- goods movement/safety; and
- a financial assessment.
Both direct and indirect impacts must be considered.
Assessments should be conducted to the extent needed to identify
and evaluate all of the significant differences among the alternatives
under consideration, to find fatal flaws, to identify the views
of interested parties, and to get some handle on mitigation costs.
At present, there is a fair amount of confusion regarding appropriate
levels of detail in each area and a manual on MIS preparation
is being developed.
The assessments are ultimately incorporated into
an evaluation procedure that includes a systematic analysis of
expected benefits and costs using both quantitative and qualitative
measures consistent with Executive Order 12893 on Principles of
Federal Infrastructure Investments.
- Cost estimating that includes capital, operating,
and maintenance costs.
- Optional DEIS. (See below.)
- Quality control procedures and processes, including
methods to ensure data and analytical quality such as independent
peer reviews and fully open public involvement processes.
In addition, sponsors of transit proposals seeking
Section 3 money must respond to FTA's project justification and
financial criteria; both transit and highway sponsors seeking
discretionary money must also comply with the evaluation criteria
of relevant Congressional committees.
Dealing with NEPA: the
Final Rule offers two options for responding to NEPA's EIS requirements:
Option 1 permits the sponsoring agency to defer the
EIS document until the later, preliminary engineering phase. The
MIS narrows the range of investment alternatives to one design
concept and scope (although more detailed design options may still
exist). It provides information for subsequent NEPA documents,
including sufficient material to support elimination of alternative
investment strategies. This is modeled after FHWA's former planning
process.
Option 2, replicating FTA's pre-ISTEA project planning,
incorporates a DEIS or Environmental Assessment (EA) into the
Alternatives Analysis (now called MIS).
Some federal officials privately predicted that projects
which were either very simple or very complex would adopt Option
2, and the remainder would choose Option 1. Their rationale was
that sponsors of easily-implementable projects would want to get
the environmental requirements over early so they could quickly
move into implementation. Sponsors of controversial projects,
on the other hand, would have to do a great deal of environmental
analysis in the MIS anyway, and might as well go the few extra
steps and comply with EIS documentation requirements.
Option 2 involves some additional up-front time and
cost because the full environmental and engineering impacts of
all alternatives have to be officially documented on an equal
basis. Also, supplemental EISs may be required if the project
changes as it moves through preliminary design. On the other hand,
some argue that this approach develops a more defensible basis
for the elimination of alternatives and the selection of one,
and dispenses of the need to repeat environmental and community
reviews.
To date, most transit MIS sponsors seem be choosing
Option 1 while sponsors oriented more to highway facilities appear
to favor Option 2.
Linkages to Other ISTEA Activities:
MISs must be closely integrated with other elements of the ISTEA
planning process as well as related requirements such as conformity
analysis. The flow chart shown in Figure 2 illustrates how MISs
will fit into the rather complicated web of new planning activities.
The focal point of major investment planning is the
MPO because all MISs must be included in both their long range
transportation plan and their TIP.
A major source of input to plan and TIP development
will be the measures and strategies produced from the management
systems, especially the Congestion Management System (CMS). If
an area does not yet have a CMS in place, is a Transportation
Management Area, and is contemplating additional single occupancy
vehicle (SOV) capacity, a special congestion analysis called an
"SOV Project Analysis" must accompany any new MIS. Other
key inputs include the results of policy studies where available;
environmental, land use studies, and other technical studies;
and, of course, contributions from stakeholders and the public.
MISs may be conducted as part of the plan preparation
or update process. Projects which emerge from this process are
then evaluated and prioritized. Those adopted move forward if
they pass the stringent test of EPA conformity analysis in non-attainment
areas. They are placed in the MPO's plan and TIP and the state
TIP, all of which must be financially-constrained. The NEPA process
is then completed and if all environmental requirements are met,
the project advances into implementation.
Ideally, the results of MISs will be available in
time for inclusion in the MPO's plan. Until the dust settles and
all MPOs have effective planning processes in place, this will
not always be the case. Being out of synch is not a fatal flaw,
however, because a "place holder" may be assumed and
included in the plan. This may be either a "No Build"
or a "most promising" alternative. Inclusion of this
assumed project allows a conformity determination and financial
constraint test to be applied to the project. Once the MIS is
completed, the plan will have to be amended to include the selected
strategy.
Grandfather Provisions:
the MIS requirements do not apply to projects where the environmental
process has been completed and a Record of Decision (ROD) or Finding
of No Significant Impact (FONSI) has been signed.
For studies underway but not completed, sponsoring
agencies need, at a minimum, to consult with FTA, FHWA, the state
DOT, transit operators, and the MPO to determine the need to revise
the study scope. Consideration will be given to:
- Nearness of the study to completion;
- Whether a reasonable range of alternatives was
considered and analyzed
- in the original study scope;
- Whether the study will produce sufficient information
to fully evaluate
- investment strategies; and
- The need for enhanced public involvement.
Major Investment Projects Can be Funded in Numerous
Ways: a wide variety of funding programs
are available to support both the planning and implementation
of major capital transportation investments as a result of ISTEA.
Planning, if it is included in the Unified Work Program
and the TIP and STIP for programming purposes, can be funded by
CMAQ, STP, NHS, or other capital funds administered by FHWA. Some
planning funds are also earmarked. It is generally recognized
that planning funds are insufficient to support MISs, and that
project money needs to be used and is eligible.
For implementation, transit and commuter rail projects
can draw upon their Section 9 and 18 allocations as well as compete
for discretionary Section 3 funds. Additional programs containing
flexible funds which may be transferred to transit include the
Surface Transportation Program (STP), the National Highway System
(NHS), the Congestion Mitigation and Air Quality program (CMAQ)
in non-attainment areas, and several others.
Major highway projects will normally be funded from
apportionments for the NHS, STP, Interstate Transfer Program,
Minimum Allocation, Donor Bonus, 90% Adjustment, or Hold Harmless
categories. Transit Section 9 funds in Transportation Management
Areas may also be transferred to highways.
New Federal Roles: Less Ongoing Oversight but
New Certification Power: FHWA/FTA see
their role in MISs as "partners" rather than "police."
For transit projects, this is a significant change from the past,
which was characterized by intensive federal oversight and review
at each major milestone.
A large portion of future quality control will be
provided by peer reviews, which FHWA/FTA are urging in several
technical areas. Other quality checks are expected to come from
the dynamic of transit agency/state/MPO partnerships, because
it is alleged that each agency will keep tabs on the others, a
premise which elicits skepticism from some observers. FTA or FHWA
will do selective reviews, although there are staff constraints,
especially within FTA. Both agencies do need to be consulted,
however, as part of the initial MIS consultation process. Projects
advancing under NEPA Option 2 will have more federal oversight
because FHWA or FTA must be a sponsor of the document.
Additionally, ISTEA breaks precedent with the past
12 years by mandating federal- (rather than self-) certifications
of all planning processes in a region. The first cycle will begin
this year.
FHWA/FTA must certify MPOs every three years and
these reviews will include MISs. Guidelines on certification are
currently under development and pilot programs are being conducted
over the summer, with citizen participation, MISs, and MPO planning
constituting three of five areas investigated. FTA Deputy Administrator
(and former STPP Director) Grace Crunican is advocating the use
of citizens as part of certification, not just of the citizen
participation programs, but of the entire planning processes.
In any event, federal officials assure they will definitely seek
consultation of major actors beyond the process and project sponsors.
Blueprint for Better Planning or a Burdensome
Federal Requirement: for the vast majority
of STPP readers, the evolving MIS requirements are a significant
change for the better.
A primary benefit of the new planning approach is
a level playing field for highways and transit. It also establishes
the framework for evaluating highway and transit alternatives
against each other. Moreover, it creates the opportunity to develop
multimodal strategies encompassing highway and transit solutions.
Another advantage is the significant impetus it creates
to bring major investment projects into the fold of comprehensive
regional planning, thereby strengthening the role of the MPO.
It is also hoped the procedures will spark greater cooperation
among state, MPO, and transit agencies.
Other benefits include assessment of a broader range
of alternatives; earlier consideration (before a decision is made)
in FHWA-sponsored projects of social, economic, and environmental
effects; a 20-year target for FTA-sponsored projects, allowing
more time to realize transit's long-term benefits; elimination
of FTA's onerous "one corridor" requirement and project
initiation threshold tests; and the potential for more uniform,
meaningful public involvement.
There are some, of course, anxious to get on with
building their projects in the face of mounting congestion, who
deplore the delays (real and perceived) that will be caused by
the new expanded studies. Others are hostile to the notion of
any additional federal planning requirements and/or fearful, especially
since so many procedures are still undefined.
It is unfortunate that it has taken FHWA and FTA
so long to agree on even the skeleton procedures we currently
have, and while their travelling seminars were immensely useful,
everyone-including those unable to attend the introductory sessions-believe
written guidance is sorely needed.
An additional shortcoming is the absence of practitioner
and public input to the development of the guidance to date, except
for comments received on the Notice of Proposed Rulemaking on
Metropolitan Planning issued in March 1993, which only addressed
the basic concept of MISs and a few key issues. While there is
no formal requirement for public participation in the development
of federal guidance, the voluntary provision of opportunities
to comment would be in keeping with the spirit of ISTEA.
Further, there are many questions about how NEPA
Option 1 will play out. Will public officials and citizens be
put through two extensive involvement processes for the same project?
If there is extensive citizen participation during the MIS, will
public interest fall off when NEPA begins, thus reducing outside
scrutiny of project development during a critical phase? Although
federal officials in Washington assure that MISs will produce
environmental and community impact information to the degree necessary
to respond to all public concerns, will this really be the case?
The budgets of some forthcoming MISs suggest otherwise. What happens
if new alternatives are discovered during NEPA, or if analyses
used to dismiss alternatives previously considered are found to
be inadequate? Might project development then take more, rather
than less, time? Answers will be evolve over the next year or
two as MISs advance through the new regulations.
Finally, many have concern about the numerous outstanding
MIS-related issues, and hope they will be resolved in the very
near future.
In spite of these concerns, overall MIS requirements
are headed generally in the right direction. Who can really argue
against spending a bit more time and effort to do good comprehensive,
participatory planning before spending tens or hundreds of millions
of dollars on a new transportation facility?
Forthcoming Federal Guidance and Assistance
There will be significant changes to MIS procedures
over the coming year as federal officials issue additional regulations
and guidance that fine-tune and expand upon existing requirements.
Interested professionals and citizens should make their views
known at every opportunity. Future modifications include:
- A new FTA Major Capital Investment Policy to
formally address the wide range of Section 3 New Start project
investment criteria called for in ISTEA, expected during the 1994
Fiscal Year. These include, in addition to cost-effectiveness,
mobility improvements, environmental benefits, operating efficiencies,
and other factors such as land use and economic development.
- A Notice of Proposed Rulemaking (NPRM) on joint
FHWA/FTA environmental procedures is scheduled for release in
late 1994. This NPRM will reflect the new MIS requirements as
well as corridor preservation guidelines. When finalized, this
rule will replace the 1987 joint regulations.
- A senior FHWA official has indicated there will
be more future guidance on public involvement, building on actual
practice and comments obtained.
- Some type of document describing how certification
will be conducted and what specific evaluation criteria will be
used has been promised by various Administration officials, although
no availability date has been set.
- Case studies of "best practices" for
major investment planning sponsored by FHWA/FTA will be out before
the end of the year. Other case studies and additional multimodal
planning research projects are being sponsored by the National
Cooperative Highway Research Program, although they will not be
available for some time.
- An MIS manual and a three-day training course
will be available by the end of the year. Two pilot courses will
be conducted in 1994 and at least 12 taught over the next two
years. Both are sponsored by the National Transit Institute with
participation by FTA and FHWA.
Suggested Federal Actions:
Support current federal efforts to obtain citizen
involvement in certification by suggesting ways this could rationally
be accomplished, participating in certification reviews in your
area, etc.
- Comment on Notices of Proposed Rulemaking such
as the forthcoming one on joint environmental procedures.
- Comment on open nonregulatory federal dockets
soliciting observations and suggestions on public involvement
and MIS procedures.
- Assess existing procedures and lobby for improvement
where necessary.
- Ask to attend one of the National Transit Institute's
MIS training programs if you or your group have the time and resources
to make such a commitment. The knowledge you will acquire in
this course will help put you on an equal footing with the
professionals.
Specific Local MIS Actions:
- Be actively involved in the initial meetings
for all MISs in your areas. Make sure the study scopes include
a full range of alternatives and address all relevant issues.
Review carefully the project's purpose and need statement and
project evaluation criteria; call on regional federal officials
if you sense a problem. If the MPO is proceeding under grandfather
provisions, add your views to the assessment of the adequacy of
prior citizen participation efforts, as well as the other key
issue areas. Urge your MPO to include citizens in the official
meetings. If this is not possible, remind them that federal regulations
call for some sort of public input in this initial stage. Think
about the pros and cons of the NEPA options, and make your views
known.
- Participate actively in whatever program is developed.
Work to get other potentially concerned individuals and groups
involved, and try to establish constructive working relationships
with the project sponsors. If necessary, remind local officials
that ISTEA regulations call for "complete information, timely
public notice, and full public access to key decisions,"
as well as early and continuing involvement of the public. Special
efforts must be made to obtain participation of those traditionally
underserved by existing transportation systems, including low
income and minority households. A Response-to-Comments record
should be maintained and MPOs must periodically monitor effectiveness.
- Take advantage of opportunities to participate
in the selection of a preferred alternative.
- Testify at meetings and hearings and lobby the
elected officials of your MPO.
- If the Locally Preferred Alternative is a project
you favor, you can often be very effective in assisting the project
sponsor in its implementation.
- Work within the MPO planning process to promote
future MISs you feel will advance your vision for your region.
- Become familiar with ISTEA and its flexible funding
programs, as well as the Clean Air Act Amendments and current
conformity regulations.
The Surface Transportation Policy Project is a nationwide network of more than 800
organizations, including planners, community development organizations, and advocacy groups,
devoted to improving the nation’s transportation system.
|