Click
here to read STPP's press release on
streamlining.
Recent
reports from the Federal Highway Administration and
the American Association of State Highway and
Transportation Officials suggest that problems
with transportation project delays will not be
solved by diluting widely-supported environmental
laws. Instead, the studies indicate that project
delivery can best be “streamlined” by addressing
intrinsic flaws in the transportation planning
process. The most effective strategy to speed
project delivery is one of the fundamental
principles of the very environmental regulations
under attack – involving stakeholders early, often
and substantively.
Are
Environmental Regulations the Problem?
There
is no doubt that many transportation projects
stretch far beyond their projected timeframe for
delivery. However, there is little evidence to
suggest that environmental laws are the cause of
most project delays. Three new studies, from the
American Association of State Highway and
Transportation Officials (AASHTO) and FHWA, attempt
to address this gap by quantifying the impact
that the NEPA process has had on transportation
projects. These studies call into question the complaints
that environmental requirements are the source of
the delays, instead finding that most delayed
projects are held up by a lack of funding and/or
lack of local political support, or by their controversial
nature (in which case the projects may merit a
go-slow approach). Other projects are held up
because of the complexity of their environmental
impacts, which rightfully require extensive review
by the appropriate natural resource agencies.
FHWA
Finds that Lack of Funding and Local Support Are
Source of Delays
The Federal Highway
Administration’s review of transportation
infrastructure projects with outstanding
Environmental Impact Statements (projects that have
yet to complete the review process after five or
more years) contradicts many of the claims made by
proponents of environmental streamlining. Most (57.5
percent) of the 89 protracted projects studied
were between 5 and 7 years old, with 13 still
awaiting a Record of Decision after more than 10
years. FHWA’s study found that the most common
reason that the projects were delayed was because of
lack of funding or low priority (32 percent), local
controversy (16 percent), or the inherent complexity
of the project (13 percent). All of these issues, as
well as changing or expanding the scope of the
project (8 percent) surpass environmental factors as
causes of project delay.
A
second FHWA study found that these delayed projects
aside, the average time required to complete the
NEPA process for EIS projects was about 3.6 years.
The median (which in this case is a better measure
because of outliers in the sample) time required was
only 3 years. It is important to note that the time
required to complete the NEPA process is not
necessarily additive to the project planning
process, and may be coincident with other phases of
the project. Regardless, the second FHWA study found
that the NEPA process typically comprises only 28
percent of the entire project development process.
AASHTO
Report Exposes Incorrect Project Classification as
Major Cause of Delays
The AASHTO study
focused not on overall project delivery, but on
state DOT experiences with the environmental review
process itself. According to AASHTO’s survey of 32
state DOTs, the vast majority of transportation projects
require only enough environmental documentation to
support a Categorical Exclusion (CE) from NEPA, the
lowest level of review. In fact, the AASHTO study
found that fully 92 percent of environmental
documents processed by state DOTs are CEs.
Environmental Assessments (EA) make up seven
percent, with full Environmental Impact Statements (EIS)
rounding out the sample at less than 2 percent. In
absolute terms, that amounts to average of only 5
EISs processed by each state in a given year.
According to the AASHTO study, of states which
experienced delays with CE preparation (63 percent
of the surveyed states), only 31 to 48 percent of
all the CEs prepared by those states were delayed.
Similarly, for the 81 percent of states which
experienced delays in EA preparation, 43 to 64
percent of the EAs prepared by those states were
delayed. In
other words, even in states which reported delays in
the environmental review process, between as many as
70 percent of documents were completed without any
delay at all.
Interestingly, the
causes of delay cited by state DOTs indicate that
the issues encountered should probably have
triggered a more rigorous environmental review
process. A review of the report indicates that some
of the projects selected by state DOTs to typify
delays were processed using lower-level
documentation than was merited. Janine Bauer of the Coalition to Defend NEPA and the
Tri-State Transportation Campaign has suggested that
perhaps the projects processed as CEs should have
been processed instead by EAs; likewise, projects
processed as EAs should have been processed through
a full EIS.
The bottom line is
that average delays for a CE or EA process were not
that burdensome. In fact, according to the AASHTO
study almost 40 percent of the surveyed states did
not experience delays in the CE process, and
almost 20 percent experienced no delays in the EA
review process. And for those projects that experienced
long delays, it was likely because they merited a
more rigorous environmental review.